October 2, 2025 · 2 min read · Adaptive Consulting Group
A Real Case Study: How Client-Side Support Protects Workday Implementations
Just as we entered E2E testing, our client was told go-live would need to be pushed 6 months (with an associated seven-figure price tag). The justification? Supposed scope creep.
Here's what really happened:
A client brought us in after they'd already parted ways with their first systems integrator (SI). A new SI stepped in and reviewed the original design artifacts to scope their work.
As part of our client-side advisory role, we assisted in reviewing and negotiating the new SI's SOW. Two key provisions were agreed upon:
- The new SI would pick up exactly where the previous SI left off.
- The new SI was responsible for reviewing all design decisions already made, and for asking clarifying questions where needed as part of their scoping.
Six months later — after the new SI had scoped their work based on existing artifacts — the new SI claimed the client had introduced "new" requirements that would delay go-live by six months, with a seven-figure price tag.
We dug in.
The "new" requirements weren't new at all. They were documented in the first SI's artifacts — the very ones the second SI had been responsible for reviewing.
So this wasn't scope creep. It was a miss.
With that evidence in hand, we:
- Held the SI accountable to the original go-live date
- Avoided unnecessary costs
- Built and managed a remediation plan to address the gaps within six weeks
The result: we protected the original timeline and budget.
The takeaway: your SI focuses on delivery. But someone has to protect your side of the table — reviewing the details, catching misses, and keeping the project honest.
Whether you're in the middle of your implementation or still in Phase 0 discussions, having the right team on your side is crucial.